Transportation Improvement Program (TIP)

TIP Executive Summary

TIP EXECUTIVE SUMMARY

The SMMPO’s Transportation Improvement Program (TIP) is the primary plan that guides all state and federally funded transportation improvements in southeastern Massachusetts. It is a federally required, 5-year document that that lists all transportation projects in the region by federal funding category, including roads, bridges, transit and alternative projects such as bicycle and pedestrian accommodations. The TIP is developed annually and is subject to amendment and adjustment at any time. Each program year of the TIP coincides with the Federal Fiscal Year, October 1 through September 30. All projects are identified by fiscal year and federal funding category and include cost. The total cost of the projects programmed in the TIP must be constrained to available funding, be consistent with the long-range Regional Transportation Plan (RTP), and include an annual element, or listing, of projects to be advertised in the first year of the TIP.

The TIP is developed annually by the SRPEDD Transportation Planning staff, acting as staff to the Southeastern Massachusetts Metropolitan Planning Organization (MPO) for southeastern Massachusetts in consultation with federal, state and local officials, adjacent MPO’s, the state of Rhode Island, transit authorities and the public. Regional priorities for projects are established by the Joint Transportation Planning Group (JTPG), which acts as the transportation policy advisory group to the MPO, and is a forum for public participation for transportation planning in the region.

The Southeastern Massachusetts MPO consists of thirteen members representing the following: Secretary of the Executive Office of Transportation and Public Works; MassDOT Highway Administrator;  Chairman of the Southeastern Regional Planning and Economic Development District (SRPEDD) Commission; Administrators of the Southeastern Regional Transit Authority (SRTA) and Greater Attleboro Taunton Regional Transit Authority (GATRA);  Mayors of Attleboro, Fall River, New Bedford and Taunton; and Members of four Boards of Selectmen in the SRPEDD Region to be elected by the SRPEDD Commission.

PROJECT DEVELOPMENT

The process of developing a project begins with identifying a need within a community. Once the need is identified, the project’s proponent (the community) should meet with SRPEDD and the staff of the MassDOT District 5 office before a project’s concept (or scope) is formally developed. An informal review can address any questions and determine any issues with a proposed project. This will also eliminate the possibility of a project getting rejected during the development process.

Public outreach is critical and should be initiated as early on in the project development as possible to ensure participation. Public outreach should be continued throughout the process, but it is particularly important early in the development of a project. A well-informed community increases the chances for acceptance and support of a project, improving the opportunity for that project to proceed and ultimately, receive funding.

PERFORMANCE BASED PLANNING AND MEASURES

Performance Based Planning and Measures requires critical changes to the planning process by ensuring that investment priorities assist in meeting performance targets that would address key areas such as safety, infrastructure condition, congestion, system reliability, emissions and freight movement. This called for the integration of a performance-based approach to decision making in support of the national goals and a greater level of transparency and accountability. The goal is to improve project decision-making and assist in more efficient investments of Federal transportation funds.

In 2016, FHWA passed a rule establishing three performance measures (PM1, PM2, and PM3) that State DOTs and MPOs must track, as required by MAP-21 and the FAST Act. MAP-21 (2012) and the FAST Act (2015) are the latest Transportation Legislation, both signed into law by President Obama to address improvements to the U.S. transportation system. PM1 is improving safety, PM2 is maintain pavement and bridge conditions and PM3 is improving efficiency of the system and freight movement, reducing traffic congestion and reducing emissions. The SMMPO adopts statewide performance measures for all three categories and has integrated them into decision making processes including evaluation criteria and programming decisions.

The Federal Transit Authority (FTA) requires any Regional Transit Agency (RTA) that owns, operates, or manages capital assets used to provide public transportation and receives federal financial assistance under 49 U.S.C. Chapter 53 to develop a transit asset management (TAM) plan. TAM Plans outline how people, processes, and tools come together to address asset management policy and goals, provide accountability and visibility for furthering understanding of leveraging asset management practices and support planning, budgeting, and communications to internal and external stakeholders. The FTA also requires RTA’s that receive federal funds under FTA's Urbanized Area Formula Grants to develop Public Transportation Agency Safety Plans (PTASP) that detail agency safety processes and procedures and set safety performance measures.

PROJECT PRIORITIZATION / EVALUATION CRITERIA

The SMMPO developed a process and set of criteria to evaluate and prioritize the region's TIP projects. All projects included in the TIP have been evaluated and assigned a priority value or score. This process is used as a management tool to identify projects of regional priority and program them accordingly in the TIP. Each project is reviewed to evaluate the impact on, or sensitivity to, each of the criteria categories including  Community Impact & Support, Maintenance & Infrastructure, Safety & Security, Mobility / Congestion,  Livability / Sustainable Development, and Environmental & Resiliency, as well to assist in meeting performance targets for safety, pavement preservation, mobility, freight movement, traffic congestion and emissions.

Through our evaluation criteria, we highlight and provide higher rankings to projects that have been identified in our RTP to ensure that existing and future needs of the regional transportation system are prioritized, as well as advance federal transportation planning factors. Many of these projects have been identified as a need in either our RTP or our regional modal plans. Some have been initiated to address infrastructure maintenance, while others may have been initiated due to a recent uptick in safety issues.

 TITLE VI AND ENVIRONMENTAL JUSTICE

SRPEDD routinely maps minority, low-income (below poverty level), Limited English Proficiency (LEP), as well as age (particularly older populations), and disability as populations of concern for our Transportation Evaluation Criteria, for public outreach purposes, for the Title VI submissions of our regional transit agencies, for transit route equity analyses and evaluations, and for other general planning purposes. As part of the requirements for the TIP we have extended these efforts into a regional project distribution / Title VI equity analyses.

If a project was located directly in or adjacent to one of the areas identified as having a population of concern by threshold or dot density as EJ, (e.g. minority, low-income), or Title VI, (e.g. LEP, older adults and/or persons with a disability), or if that project directly connected and/or served the identified area, we included the project as falling within one of these areas. We conducted two separate analyses, for the current FFY2022-2026 TIP and for the look-back period of the FFY2017-2021 TIP. Our results for the current FFY2022-2026 TIP show that 13 out of the 14 projects in the TIP fall within, directly connect, or serve Title VI or EJ populations which is 93% of the current projects. Our results for the look-back period of the FFY2017-2021 TIP show that 16 out of the 17 projects in the TIP fall within, directly connect or serve Title VI or EJ populations, which is 94% of the look-back projects.

FUNDING CATEGORIES

Federal funding categories for highway and bridge projects through the FHWA include Bridge (BR), Congestion Mitigation/Air Quality (CMAQ), Earmarks, Emergency Relief (ER), Federal Lands Access Program (FLAP), Ferry Boat Formula Program (FBP), Highway Safety Improvement Program (HSIP), National Highway Freight Program (NHFP), National Highway Performance Program (NHPP), Non-Federal Aid (NFA),Railroad Highway Crossing Program (Section 130), Surface Transportation Block Grant Program (STBG), and Surface Transportation Block Grant Program – Transportation Alternatives (STBG-TA).

Federal Transit Administration funding programs include Section 5307 Urbanized Area Formula Funding Program, Section 5310 Enhanced Mobility of Seniors and Individuals with Disabilities, Section 5311 Formula Grants for Rural Areas, Section 5337 State of Good Repair Grants, and Section 5339(a) Bus and Bus Facilities.

State and local funding programs include Regional Transit Authority Capital Assistance Program (RTACAP), Mobility Assistance Program (MAP), State Contract Assistance (SCA), Transportation Development Credits (TDC), and Transportation Bond Bill Funding.

The MassDOT Office of Transportation Planning, in consultation with the Regional Planning Agencies, provides each region with yearly targeted federal funding levels for regional priority projects.  The table below displays all highway targets and programmed amounts.


Federal Highway Federal Aid Financial Plan for FY21-25 TIP

Federal Fiscal Year 2022 2023 2024 2025 2026
Total Regional Federal Aid Funds Available  

$22,246,785

 

$22,732,674

 

$23,030,625

 

$22,492,971

 

$21,908,871

STBG Programmed $11,570,040 $16,442,077 $20,410,819 $9,872,740 $19,238,229
HSIP Programmed $0 $0 $0 $0 $0
CMAQ Programmed $9,554,273 $3,371,115 $0 $11,177,235 $0
STBG-TA Programmed $0 $0 $0 $0 $0
Total Programmed $21,124,313 $19,813,192 $20,410,819 $21,049,975 $19,238,229
Balance $1,122,472 $2,919,482 $2,619,806 $1,442,996 $2,670,642

Transit projects that are programmed in the TIP represent both apportioned and discretionary items. The total amounts as displayed in the tables below and on the following pages, represent total federal, state and local contributions for GATRA & SRTA by fiscal year.


GATRA Federal Transit Financial Plan for FFY2022-2026: Federal Fiscal Year 2022

FTA Program Federal Funds Programmed State Funds Programmed   TDC Local Funds Programmed Total Funds Programmed
5307 $6,420,000 $2,055,000 $0 $0 $8,475,000
5337 $0 $0 $0 $0 $0
5339 $0 $0 $0 $0 $0
Other Non- Federal $0 $0 $0 $528,000 $528,000
Totals $6,420,000 $2,055,000 $0 $528,000 $9,003,000

GATRA Federal Transit Financial Plan for FFY2022-2026: Federal Fiscal Year 2023

FTA Program Federal Funds Programmed State Funds Programmed   TDC Local Funds Programmed Total Funds Programmed
5307 $6,180,000 $1,995,000 $0 $0 $8,175,000
5337 $1,013,370 $0 $0 $253,343 $1,266,713
5339 $0 $0 $0 $0 $0
Other Non- Federal $0 $0 $0 $530,000 $530,000
Totals $7,193,370 $1,995,000 $0 $783,343 $9,971,713

GATRA Federal Transit Financial Plan for FFY2022-2026: Federal Fiscal Year 2024

FTA Program Federal Funds Programmed State Funds Programmed TDC Local Funds Programmed Total Funds Programmed
5307 $6,070,000 $2,005,000 $0 $0 $8,075,000
5337 $1,030,800 $0 $0 $257,700 $1,288,500
5339 $0 $0 $0 $0 $0
Other Non- Federal $0 $0 $0 $530,000 $530,000
Totals $7,100,800 $2,005,000 $0 $787,700 $9,893,500

GATRA Federal Transit Financial Plan for FFY2022-2026: Federal Fiscal Year 2025

FTA Program Federal Funds Programmed State Funds Programmed   TDC Local Funds Programmed Total Funds Programmed
5307 $6,670,000 $2,155,000 $0 $0 $8,825,000
5337 $1,048,530 $0 $0 $262,133 $1,310,663
5339 $1,040,000 $260,000 $0 $0 $1,300,000
Other Non- Federal $0 $0 $0 $532,000 $532,000
Totals $8,758,530 $2,415,000 $0 $794,133 $11,967,663

GATRA Federal Transit Financial Plan for FFY2022-2026: Federal Fiscal Year 2026

FTA Program Federal Funds Programmed State Funds Programmed TDC Local Funds Programmed Total Funds Programmed
5307 $6,850,000 $2,275,000 $0 $0 $9,125,000
5337 $0 $0 $0 $0 $0
5339 $0 $0 $0 $0 $0
Other Non- Federal $0 $0 $0 $532,000 $532,000
Totals $6,850,000 $2,275,000 $0 $532,000 $9,657,000

SRTA Federal Transit Financial Plan for FFY2022-2026 TIP: Federal Fiscal Year 2022

FTA Program Federal Funds Programmed State Funds Programmed   TDC Local Funds Programmed Total Funds Programmed
5307 $4,644,457 $3,715,957 $0 $15,000 $8,375,414
5339 $144,000 $36,000 $0 $0 $180,000
Other Non- Federal $789,566 $234,892 $0 $0 $1,024,458
Totals $5,578,023 $3,986,849 $0 $15,000 $9,579,872

SRTA Federal Transit Financial Plan for FFY2022-2026 TIP: Federal Fiscal Year 2023

FTA Program Federal Funds Programmed State Funds Programmed  TDC Local Funds Programmed Total Funds Programmed
5307 $11,541,357 $11,272,857 $0 $15,000 $22,829,214
5339 $172,000 $43,000 $0 $0 $215,000
Other Non- Federal $750,000 $750,000 $0 $0 $1,500,000
Totals $12,463,357 $12,065,857 $0 $15,000 $24,544,214

SRTA Federal Transit Financial Plan for FFY2022-2026 TIP: Federal Fiscal Year 2024

FTA Program Federal Funds Programmed State Funds Programmed  TDC Local Funds Programmed Total Funds Programmed
5307 $12,200,801 $11,910,581 $0 $15,000 $24,126,382
5339 $144,000 $36,000 $0 $0 $180,000
Other Non- Federal $750,000 $750,000 $0 $0 $1,500,000
Totals $13,094,801 $12,696,581 $0 $15,000 $25,806,382

SRTA Federal Transit Financial Plan for FFY2022-2026 TIP: Federal Fiscal Year 2025

FTA Program Federal Funds Programmed State Funds Programmed  TDC Local Funds Programmed Total Funds Programmed
5307 $13,989,635 $13,700,135 $0 $15,000 $27,704,770
5339 $144,000 $36,000 $0 $0 $180,000
Other Non- Federal $750,000 $750,000 $0 $0 $1,500,000
Totals $14,883,635 $14,486,135 $0 $15,000 $29,384,770

AMENDMENTS, ADMINISTRATIVE ADJUSTMENTS & ADMINISTRATIVE MODIFICATION

The TIP may be modified after it has been endorsed due to project schedules, changes in cost estimates and financial constraints.

All formal actions of the SMMPO must result from a vote taken at a public meeting and conform to SRPEDD's Public Participation Program (PPP). Amendments to the TIP require the approval of the SMMPO and are subject to the public participation process requiring a public meeting, a 21-day public comment period and a process of public notification. Administrative adjustments to the TIP require the approval of the JTPG or the SMMPO by majority vote of those present at a duly constituted meeting, where the proposed administrative adjustment or modification was part of the agenda. An Administrative Modification is a revision to the TIP that is minor enough in nature to require neither a public process nor FHWA/FTA approval, but that does involve a notification to federal partners.

AIR QUALITY CONFORMITY DETERMINATION

The 1990 Clean Air Act Amendments (CAAA) require metropolitan planning organizations within nonattainment and maintenance areas to perform air quality conformity determinations prior to the approval of Long-Range Transportation Plans (LRTPs) and Transportation Improvement Programs (TIPs).

The SMMPO MPO has prepared conformity determination for the 1997 Ozone National Ambient Air Quality Standards in accordance with Environmental Protection Agency’s and Massachusetts’ latest conformity regulations and guidance. This conformity determination process demonstrates that the FFY 2022-2026 Transportation Improvement Program and the 2020-2040 Regional Transportation Plan meet the Clean Air Act and Transportation Conformity Rule requirements for the 1997 Ozone NAAQS, and have been prepared following all the guidelines and requirements of these rules during this time period.

GREENHOUSE GAS EMISSIONS

The transportation sector is the single largest emitter of greenhouse gases, accounting for over a third of GHG emissions, and therefore the transportation sector was a key focus of the Massachusetts Clean Energy and Climate Plan for 2020. The implementation plan established initial targets for overall, statewide GHG emissions.

The SMMPO seeks to balance highway system expansion projects with other projects that support smart growth development and promote public transit, walking and bicycling. This regional TIP includes an evaluation of all projects that would have an impact on greenhouse gas emissions.

A Greenhouse Gas (GHG) assessment is conducted for each TIP project. When the project is in an early stage, the project’s impact on GHG is reported as an expected impact. When more information is available, a qualitative or quantitative assessment is performed based on the project type. Generally quantitative assessments are performed on bicycle and pedestrian infrastructure projects, bus replacement projects, new/additional transit service projects, park and ride lot projects, traffic operational improvement projects, alternative fuel vehicle procurements, anti-idling strategies, bike share projects, induced travel projects, speed reduction programs, transit signal priority projects, and truck stop electrification projects.

After determining if a project should be quantified, Congestion Mitigation and Air Quality (CMAQ) spreadsheets provided by MassDOT are used to estimate the impact of a project. If a project does not fall into a category for a quantitative assessment, a qualitative assessment is performed and the results are reported as an estimated increase, decrease or no impact.

For additional information and details please see the FFY2022-2026 TIP in its entirety on our website. To get involved or for more information or questions please email Lisa Estrela-Pedro at lestrela@srpedd.org.